|
|
» Cracks in Concrete
» Hot Weather Concreting Practice
» Techniques of Cold Weather Concreting
» Techniques of Curing Concretes
» The Effect of Excess Water in Concrete
» Step-by-Step Guide to Laying Concrete
|
Cracks in concrete
The cracking phenomenon
When placed concrete typically contains more water than is required for hydration of the cement. As the concrete hardens and starts to lose the excess water, shrinkage begins. If the concrete is unrestrained, no cracks will develop. But it is virtually impossible to support a structure of any appreciable size without some restraint.
The cracking phenomenon is complex and depends upon a number of things; rate and amount of drying, drying shrinkage, tensile strength, tensile strain, creep, elasticity, degree of restaint, and other factors.
While most types of cracking do not affect structural stability or durability, all cracks are unsightly and in extreme cases cracking can reduce the use and servicability of the structure. For this reason, cracking should be kept to a minimum.
In the laboratory, drying shrinkage tests are the most easily and most frequently performed tests in relation to shrinkage/cracking problems. However, there is sometimes too much emphasis on the drying shrinkage of hardened concrete as the criterion of susceptibility to cracking.
Drying shrinkage alone is influenced by many factors - water/cement ratio; amount, fineness and composition of cement; mineral composition, stiffness, shape, surface texture, and grading of the aggregate; characteristics and amount of any admixture; size and shape of the concrete mass; and conditions of humidity and temperature.
Preventative measures at the time of placing and curing remain the best means of minimizing cracking.
Some Types and Causes
In most cases where cracks appear in concrete the crack can be identified and the cause of cracking established. An extensive survey carried out revealed that concrete cracking can be attributed to the following:
- construction and supervision problems - approx. 36%
- design defects approx. 27%
- ambient conditions (temperature, humidity, etc.) - approx. 21%
- quality of materials - approx 17%
In addition all cracks can be grouped into two broad categories:
- cracks occurring before and during hardening
- cracks occurring after hardening of concrete
Recognising Cracks
- Shrinkage cracks avoid by cutting contraction joints along dotted lines
- Shrinkage cracks caused by stress concentration at corners - prevent by placing expansion joint along dotted line, or by using reinforcing steel
- Settlement cracks caused by movement of sub-grade or footings
- Cracks due to heaving under the slab through poor drainage of sub-grade
- Expansion cracks prevent by placing expansion joints at dotted lines
- Shrinkage cracks in feathered sections. Narrow feathered sections should be avoided
- Plastic shrinkage cracks, due to quick loss of water to dry sub-grade or to the atmosphere
- Shrinkage cracks at door or window corners avoid by use of reinforcing steel or (in solid concrete walls) by careful placement of low-slump concrete
| |
 |
 |
|
| Inside |
Outside |
|
|
| |
| Cracks before and during hardening |
| |
Plastic shrinkage cracks occur when wind velocity, low relative humidity, high ambient temperature, or a combination of all three, cause water to evaporate from a concrete surface faster than it can be replaced by bleeding to the surface. The rapid evaporation which causes this cracking can be checked by windbreaks, shading and surface treatments.
Vertical cracks may be caused by the settlement of concrete around reinforcing bars. Such cracks occur when the concrete near the surface takes a partial set while the rest of the concrete is still able to settle. Cracking of this type can be identified by a pattern which follows reinforcement. Thus cracks can often be prevented by revibration of concrete. Sloping cracks sometimes appear when coarse aggregate particles near the surface form a skeleton in which cement paste can settle and separate Once again, vibration and revibration will reduce or prevent cracking.
Relatively small movements of formwork in the early stages of hardening will cause cracks. Swelling or bulging of timber, springing of nails, clumsy or excessive use of vibrators are the common causes of form movement resulting in irregular cracks.
Wide cracks, sometimes extending through the slab, occur when sub-grade subsides before concrete has developed strength. This may occur because the sub-grade is not level and well compacted, or is muddy, or is unstable for any other reason. |
| |
 |
Typical three-branch plastic skrinkage crack, caused by too rapid loss of water soon after concrete has been finished |
| |
|
 |
When concrete settles over obstructions such as reinforcing bars, cracks may appear along the surface above the obstruction. Avoid this by using low-slump concrete and vibrating well throughout the depth of formwork |
| |
|
 |
Slight bulging or shifting of forms may cause cracking. Usually the concrete surface will be slightly distorted if form has moved |
| |
|
 |
Uneven sub-grade, or rupture of any covering over
subgrade may allow concrete to shift while settling.
Deep cracks usually result. |
| |
|
Cracks after hardening
This category covers the performance of concrete whose shape can no longer be altered without damage It includes cracks caused by drying shrinkage, as well as those which result from the temperature movements which take place in all materials exposed to the elements. Unless the structure concerned permits movements of its members without development of excessive stresses, extensive cracking often may occur. Crazing cracks after hardening can result from excessive floating which tends to draw water and cement to the surface, which then comprises weak concrete subject to high shrinkage stresses. More often, they result from poor curing. Other cracks which occur after hardening can be caused by lack of adequate reinforcement at corners, insufficient depth of concrete over bends in reinforcement, nesting of reinforcing steel in concrete, lack of expansion and contraction joints.
Slots and joints
Shrinkage cracks cannot always be prevented, but they can be controlled by making planes of weakness to establish the direction of cracking when contraction occurs. This is done by cutting slots one third the thickness of the slabs, and is done as soon as the concrete is hard enough to resist damage by the saw. Cracking, if it occurs, will then occur neatly beneath the line of the slot. (If the cutting is left much later than the point of time mentioned, surface cracks may suddenly appear, veering off the line of sawing.)
The contraction slots should be cut at logical points of stress in paths, at ½ to 2 metre intervals (lightweight paths can be scored with a double edger); in driveways or large floors, at 5 to 7 metre intervals. Where the floor is divided into bays by columns, the joints may be placed from column to column for better appearance (see illustration). However, they should not be more than 7 metres apart unless slabs contain substantial steel reinforcement. Expansion joints, or isolation joints, usually consist of pre-moulded tar material 10mm thick, as deep as the slab, and as long as the slab. They should be placed where paths or driveways meet, and where slabs meet a column base, wall, or any other mass which will resist expansion in that direction (see illustration). |
| |
 |
Contraction joints cut one-third the depth of the slab permit free contraction and help establish direction of any cracking |
| |
|
 |
A standard method of positioning contraction and expansion joints in a floor divided into bays by columns |
| |
|
|
Water - Added and evaporated
To enable it to be poured and worked, nearly all concrete contains more water than is needed for hydration of the cement. The addition of water to ready mixed concrete increases the likelihood of segregation and excessive bleeding, which will cause the concrete surface to be porous, weak, and prone to crack. On the other hand, during curing, too-rapid evaporation of water from the surface will also make the surface prone to crack, and ponding, fog-spraying, or water-retaining covers should be applied continuously throughout the process. The supervisor's perennial problem is to make his men understand that too much water at the placing stage is as harmful as too little at the curing stage.
Summary
The majority of cracks occur within 2-3 days after concrete has been placed. These are preventive measures which will minimise cracking in that period:
- see that sub-grade is well-compacted
- check that form work is firm
- ensure that sub-grade and form work are moist before pouring
- do not add water to ready-mixed concrete in placing
- compact low-slump mixes well
- cut sufficient contraction joints to allow for shrinkage
- provide expansion joints where necessary
- start curing as soon as possible
- maintain proper curing for an adequate period.
By the use of the procedures in this publication and by exercising proper care you will obtain the best performance from Ahlcon Readymix Concrete. Ahlcon Readymix Concrete operates laboratories throughout India. These laboratories have trained technical staff who are available to answer any technical enquiries you may have and assist in designing concrete mixes specifically for your needs.
|
| |
| »Top |
|
|
Hot Weather Concreting Practice
Hot weather problems
During hot weather conditions a number of on-site factors can work against deriving optimum performance from concrete. When combined with low relative humidity and strong winds placing and finishing requires special care.
However, provided your premixed concrete producer supplies concrete made with sound, well-graded aggregates, with an adequate cement content, and with the precise water content needed to give sufficient workability for efficient placing and consolidation, there should be few problems in placing and finishing if reasonable care is taken.
There are a few simple precautions which will protect "summer" concrete and will make it easier to obtain the best concrete job.
The main problems arising during summer concreting are (a) to prevent the early loss of water from concrete, and (b) to prevent early setting through too-rapid drying. If these problems are not anticipated, there may be -
- strength reduction
- crazing or cracking
- shrinkage cracks
- finishing difficulties.
Precautions for Hot Weather Concreting
Planning ahead and preparation for each job will minimise the problems mentioned above, and will avoid irritating on-site delays.
Probably any experienced concrete contractor will know why it is sound sense to observe each one of the precautions set out below. Put together, they provide a time-saving and work-saving check list for supervisors and, perhaps, a guide for people not yet familiar with hot weather conditions in this country -
- A first and very necessary step in retaining the water in mixed concrete (as delivered by the producer) is to thoroughly moisten the sub-grade, reinforcing steel and wooden forms before placing the concrete.
- Avoid delay in placing the concrete. Have sufficient labour and equipment on hand to perform the placing quickly.
- Don't order or try to place more ready-mixed concrete than you can reasonably expect to finish and cover.
- Discharge concrete as soon as possible from the Ahlcon Readymix truck. Excessive temperature build-up may result from prolonged agitation on the job-site.
- Care should be exercised with vibrators, to avoid over- vibration. Five to fifteen seconds of vibration, depending on the depth of the concrete, should give the desired compaction
- During a pour in very hot weather, try to shade the concrete from direct sunlight.
- Use wet coverings until final finishing can be completed, or spray with an alaphatic curing compound.
- If a flat finish is required, uncover only a small section immediately ahead of the finishers. Cover again at once after final finish.
- Keep covers wet.
- Have sufficient labour and equipment on hand to finish the concrete.
- In cases of extreme hot weather it may be wise to start jobs in the afternoon to take advantage of lower temperatures in the evening.
- Keep a "weather eye" open. A gentle breeze on a hot, dry day cannot be ignored. The evaporation rate of moisture from freshly placed concrete will increase to four times when wind velocity rises from zero to only 15km per hour on a hot day.
- Start curing as soon as possible, using a method that will ensure moisture losses are minimised and protects the concrete from temperature extremes.
|
 |

Sub-grade should be damp, but not muddy. Saturate beforehand then sprinkle again just before concrete is placed.
 Discharge concrete from waiting trucks as soon as possible. Heat evolution from cement hydration and continuous agitation results in temperature rises in the concrete which can cause a rapid loss in workability.
 In very hot weather, shade concrete from sunlight or use wet coverings until finishing can be completed. |
Curing techniques
Curing is the protection of fresh concrete from evaporation and temperature extremes which might adversely affect cement hydration. If concrete is to gain potential strength and durability it must have -
- Sufficient water for the hydration of the cement, and
- A temperature conducive to maintaining this chemical reaction at a rapid, continuous rate.
To ensure the existence of these conditions, the concrete must be protected from the harmful influences of wind, sun and variable weather. As 23ºC is considered the ideal temperature for hydration, it is desirable to maintain concrete temperature at or about this figure as curing proceeds.
Concrete curing techniques fall into two groups
- those designed to prevent loss of water, such as the application of impermeable membranes; and those that supply moisture throughout the early stages of the hydration process, such as ponding or the application of wet sand or hessian.
Selecting the method of curing is generally a matter of economics, but another consideration is that the method used should cause the least interference to other operations on the site. |
 |

Water can be retained longer by using an absorptive cover. |
Absorptive covers
An absorptive medium such as sand, hessian or canvas will hold water on the concrete surface while curing progresses.
Any such medium must be kept damp constantly during the curing period, for if drying is permitted the cover itself will absorb moisture from the concrete. Alternate drying out and wetting of the cover may cause cracking.
The use of sawdust as a cover is not advisable, for it has on occasion retarded the hardening of concrete through the action of sugar in the sap still present in the sawdust.
Water addition curing
Theoretically, flooding, ponding or mist spraying are better than the retention methods mentioned above. But they are not always practical because of job conditions.
Care should be exercised to prevent large temperature differentials between the concrete mass and curing environment so as to avoid potential cracking due to temperature gradients within the concrete. This is generally known as thermal shock cracking.
Water retaining materials
Chemical or liquid membranes are gaining in popularity because they are convenient to use. They can be applied by hand or power sprays.
These membranes come in four general categories: wax based; chlorinated-rubber based; resin based and PVA based.
When it dries, a membrane compound forms a vapour seal on the surface of the concrete, the water in the concrete is sealed in and good curing conditions are established.
Care should be exercised in the selection of an appropriate membrane coating in that compatibility with the intended applied finish to the concrete must be taken into account. |
 |

Chemical or liquid membranes reduce evaporation by seating the concrete. |
Mechanical barriers
The use of waterproof building papers or plastic film (polyethylene sheeting) will also prevent the evaporation of moisture from concrete.
Any material used as a mechanical barrier to evaporation should be placed over the concrete as soon as the placing of it will not cause surface damage. The edges of the material should overlap several inches, and should be tightly sealed with sand, tape, mastic or wooden planks.
It is good practice, though one not always followed, to moisten the surface of the concrete with an atomising spray of water immediately prior to placing of the sheeting on the concrete. |
 |
 Mechanical barriers should be placed over concrete as soon as the surface is set. |
Avoid adding water to mixes
When handling low-slump concrete in hot weather, the placers will often ask for "more water". Excessive water added to the components of a mix can destroy the quality of poured concrete. Wet concrete has a tendency to segregate and exhibit excessive bleeding properties. As the water bleeds to the surface and under certain conditions evaporates quickly cracking can and does result.
Better workability and longer setting times are best achieved using special chemical admixtures.
Inform your Ahlcon Readymix supplier of your special requirements, as most of these admixtures must be added at the concrete plant.
Effects of too much mixing water
ADVANTAGES OF ADDED WATER
DISADVANTAGES OF ADDED WATER
- Lower compressive strengths
- Segregation of the concrete mix under certain conditions resulting in variable quality throughout the concrete mass.
- Cracking - with too much water, there will be lower tensile strength, and a tendency towards high shrinkage and subsequent cracking.
- Dusting and scaling - bleeding of excess water brings too many fines to the surface of floors
- Sand streaks. Excess water bleeding up the sides of forms washes out cement paste and leaves an unsightly streaked surface.
- Contamination. Too much water in concrete placed on grades causes contamination from the subgrade with the concrete leading to an array of quality problems
- Permeability. Voids left as excess water evaporates invite water to seep through walls and floors
- Dead losses - costly repairs, or in extreme cases, demolition and re-building at contractor's expense.
Reasons for curing
To sum up the advantages of careful control of moisture and temperature in curing
- The strength of concrete increases with age if curing conditions are favourable. Compressive strength of properly cured concrete is 80 to 100 per cent greater than the strength of concrete which has not been cured at all.
- Properly cured concrete surfaces wear well.
- Drying shrinkage cracking is reduced.
- Greater watertightness of constructions is assured.
Points to keep in mind when curing
- Start curing operations as soon as possible after concrete has been placed
- For proper curing concrete needs moisture
- Continuity in curing is a must, alternations of wetting and drying promote the development of cracking
- If during curing the concrete is allowed to dry out, as may happen in hot weather, the chemical change stops right at the point where the concrete loses its moisture.
- The ideal curing temperature is 23°C.
- Cure concrete for at least 7 days.
|
 |
 Note: 35oC is the maximum concrete temperature for field placing alowed under AS1379. |
The vicious cycle in inadequate curing must be obvious. If enough water evaporates from the concrete before it has attained its maximum strength, there will not be sufficient water remaining in the concrete to fully hydrate the cement and so achieve that maximum strength.
|
| |
| »Top |
|
|
Techniques of Cold Weather Concreting
Cold weather concreting problems
Few areas in Australia experience temperatures low enough to
warrant elaborate and expensive protection of freshly-placed
concrete which are common practice in Europe and North America.
However occasional frosts, abrupt drops in ambient temperature,
and/or prolonged periods of cold weather, do occur in our winter
seasons. Harmful effects of these conditions on fresh concrete can
be avoided by relatively simple measures in ordering, placing and
curing.
Hardening of concrete is a chemical process and as in many
chemical reactions the rate is temperature dependent. The lower the
temperature, the slower is the process of hardening or setting of
concrete.
At an ambient temperature just above 0°C the development of
strength in unprotected freshly-placed concrete is very slow. If the
ambient temperature drops below 0°C some of the water in the
concrete may freeze; setting will virtually stop until it thaws, and
this interruption of hydration increases porosity and reduces
strength and durability.
Because some heat is generated during the hydration process,
ordinary concrete has a minor inherent resistance to the freezing of
its water after placing. But when the temperature of the concrete
surface itself falls below freezing point, the water near the
surface will solidify, increasing in volume and causing high
pressures in concrete, which is no longer plastic. Scaling or
spalling will follow, and will be severe if several freezing and
thawing cycles occur.
Reduced Permeability
Of all the factors affecting freeze resistance of concrete,
permeability plays by far the most important role. Impermeable
concrete has only small amounts of free moisture in its pores and
thus the destructive action of freezing and expanding water is
largely eliminated. There are three basic methods of reducing
permeability and hence increasing freeze resistance of concrete,
viz:
- Use of air-entraining admixtures. These prevent
formation of continuous capillary passages by replacing them
with minute, discrete (not interconnected) air voids.
- Reduction in water to cement ratio, which in turn
reduces the bleeding rate (and bleeding capacity) of
concrete. The presence of relatively large and continuous
capillaries is usually closely related to bleeding of
concrete.
- Use of pozzolans, such as fly ash, in order to replace
part of the cement (generally fifteen to twenty per cent)
resulting in a slight increase in the amount of
|
 |

|
hydraulically active material. Pozolans react
with soluble products of cement-water reaction and form
water-insoluble and hence water-impermeable substances. With
proper use of pozzolans, permeability of concrete can be
reduced by a factor larger than ten. However, as pozzolanic
reaction is very temperature- sensitive, use of fly ash can
reduce the rate of strength gain (depress early strength) in
cold water concreting.
|
Water is at its maximum density at approximately 4°C, i.e. it has
minimum volume for a given mass at that temperature. Therefore
disruption to hardened concrete structure due to the increase in
volume of freezing water (or ice) is possible at very low
temperatures only. Hence, at temperatures above 5°C, long-term
durability and strength of concrete are not going to suffer
(ultimate strength of concrete moist cured in cool storage is
generally superior to conventionally cured concrete).
Early Age Strengths
However, the rate of strength gain of concrete at low
temperatures is relatively slow (refer to the graph above) and this
can adversely affect construction pace (delay in removal of
formwork, disruption to "critical path" etc...). To overcome this
problem, several methods of producing higher early strength can be
employed.
The methods of achieving faster setting times and high early
strengths of concrete vary with particular applications, viz: local
climatic conditions in different regions, availability of certain
raw materials (e.g. cement and admixture types etc.), as well as
layout of plant and machinery. Therefore it is important to discuss
all the special requirements of cold weather concreting with
Ahlcon RMC production or technical staff.
These methods include:
- The use of accelerating admixtures
- The introduction of hot water at the concrete batch plant
- Covering or heating of form areas prior to pouring.
This particularly applies to the inclusion of set accelerating
admixtures such as calcium chloride, improper use of which can
produce an adverse effect both in plastic and in hardened concrete.
Preparing for pouring
Small oversights at the pouring stage can result in disputes and
dissatisfaction over cold-weather concreting.
After rain, free water lying on the surface, or lying in porous
sub-grades, will be slow to evaporate, and its total volume may be
substantial. If the concrete pour causes much of the free (and cold)
water to accumulate in one end or corner of formwork and combine
with low-slump concrete there, a critical weakness may develop.
Accumulations of ice at the bottom of holes prepared for concrete
piers may be overlooked, and structural movement may follow.
Concrete should not be poured on frozen ground, or on reinforcing
steel or formwork which has a temperature near freezing point.
Covering or heating of form areas prior to concreting, a not
uncommon winter practice in Hobart, parts of Victoria, the Snowy
Mountains area, and Canberra, is less usual in coastal areas further
north. But successive frosts in Sydney's western suburbs can cause
ground temperatures there to drop to low levels, particularly where
ground is shaded throughout the day by adjacent buildings or trees.
In Sydney generally, if form areas are covered overnight, frosts
will not delay pouring the following morning. Wherever possible,
monolithic floor finishes should be placed after walls and roof
enclose the area.
Maintaining temperature
After placing concrete in cold weather its temperature must be
maintained at a consistent high level if strength gain is to be
normal.
Where ambient temperatures can be expected to be near or below
freezing point for several days, insulation by batts or commercial
blankets is indicated. Such insulation should be in close contact
with surfaces and forms, and should itself be covered with strong,
moisture-proof material. Steel projecting from forms should also be
covered where possible.
Where minimum daily temperatures are unlikely to fall much below
5°C, less elaborate means of maintaining concrete temperatures can
be used. It may be sufficient to lay waterproof paper on the form
area, cover the paper with straw or sawdust to a depth of three or
four inches and cover this with more waterproof paper, or sufficient
merely to create dead air space between the form area and tarpaulins
suspended above it. Heating and curing by exhaust system requires
the building of an enclosure to keep cold air out. Any breakdown in
the process may permit surface icing or rapid temperature changes in
the concrete, with subsequent cracking.
Heating by fires placed at intervals provides uneven temperatures
and is not favoured. The absorptive ability of cold air is low but
increases rapidly as the air is heated. If heated air causes
excessive evaporation from the concrete surface, shrinkage cracks
will occur. Also, carbon dioxide produced by fires may carbonate the
concrete surface, causing it to become chalky.
Five or six days after pouring, insulation should be removed at a
time of day and in a manner which will allow the drop in temperature
of any area of the concrete to be gradual. Membrane-curing compounds
can be applied at this stage if necessary.
Stripping formwork
Strength gains of concrete will vary with the type of cement and
type of mix, the use of accelerators, the ratio of mass to surface
area, and other factors apart from temperature.
Generally it will be advantageous to leave formwork in position
longer than the minimum period specified. Formwork will foster
rather than retard curing in cold weather, and while it remains in
position it is a reminder that any one section of a new slab should
not be loaded too early or too abruptly.
Concrete mixes with some air entrainment, with the minimum
practical water content and adequate cement, minimise problems in
cold-weather work.
The ability of the concrete supplier to design and supply
consistent batches of such mixes is important. The need to ensure
that the mixes are at or close to ideal curing temperature is no
less important.
|
| |
| »Top |
|
|
Techniques of Curing
Concretes
Curing Techniques
Curing is the protection of fresh concrete from evaporation and
temperature extremes which might adversely affect cement hydration.
If concrete is to gain potential strength and durability it must
have -
Sufficient water for the hydration of the cement, and a
temperature conducive to maintain this chemical reaction at a rapid,
continuous rate.
To ensure the existence of these conditions, the concrete must be
protected from the harmful influences of wind, sun and variable
weather. As 23°C is considered the ideal temperature for hydration,
it is desirable to maintain concrete temperature at or about this
figure as curing proceeds.
Concrete curing techniques fall into two groups - those designed
to prevent loss of water, such as the application of impermeable
membranes; and those that supply moisture throughout the early
stages of the hydration process, such as ponding or the application
of wet sand or hessian.
Selecting the method of curing is generally a matter of
economics, but another consideration is that the method used should
cause the least interference to other operations on the site
Evaporation from concrete freshly placed on
site
The graph shows the effects of air temperature, humidity,
concrete temperature, and wind velocity together on the rate of
evaporation of water from freshly placed and unprotected
concrete.
Example:
- With air temperature at 25°C
- With relative humidity at 40%
- With concrete temperature at 25°C
- With a wind velocity of 20 km/hr the rate of evaporation would
be 1.1 kg/m² hr. The highlighted line plots the example described
above. The nomogram can be used for calculation of evaporation
rates if other variables are known.
To determine the evaporation rate from the graph enter the graph
at the air temperature (in this case 25°C and move vertically to
intersect the curve for relative humidity encountered - here 40%.
From this point move horizontally to the respective line for
concrete temperature - here 25°C. Move vertically down to the
respective wind velocity curve and then horizontally to the left to
intersect the scale for rate of evaporation.
Trouble with plastic cracking is potentially in the making when
the rate of evaporation exceeds 0.5 kg/m² hr.
When the evaporation rate exceeds 1.0 kg/ m² hr precautionary
measures to prevent plastic shrinkage are almost mandatory.
Water retaining materials
Chemical or liquid membranes are gaining in popularity because
they are convenient to use. They can be applied by hand or power
sprays.
These membranes come in four general categories: water based;
chlorinated-rubber based; resin based and PVA based.
In addition to the above classification, curing compounds can be
purchased in three different types: Type 1 is clear and translucent
without dye; Type1-D clear and translucent with fugitive dye; Type
2, white pigmented.
The clear types usually preferred for surfaces that must be
architecturally attractive have one major disadvantage; it is
difficult to determine whether they have covered an area of concrete
completely.
White compounds reflect the rays of the sun, greatly
reducing the surface temperature of the concrete. The white
colour will make the covered areas easily distinguishable.
After a few days of exposure to direct sunlight the colour
will fade.
When it dries, a membrane compound forms a
vapour seal on the surface, and the hardness of the sealer
film when dry, are important factors. |
 |
 Chemical or liquid membranes
reduce evaporation by seating the concrete.
|
Care should be exercised in the selection of an appropriate
membrane coating in that compatability with the intended applied
finish to the concrete must be taken into account.
Mechanical barriers
The use of waterproof building papers or plastic film
(polyethylene sheeting) will also prevent the evaporation of
moisture from concrete.
Pigmented polyethylene sheeting provides a good curing medium as
it is impervious to moisture, light in weight, and can be re-used
under good conditions.
Plastic sheeting also has the advantage of flexibility. It is
easy to drape over complex shapes, and the progress of curing and
condition of the concrete can be checked easily at any time.
Any material used as a mechanical barrier to
evaporation should be placed over the concrete as soon as the
placing of it will not cause surface damage. The edges of the
material should overlap several inches, and should be tightly
sealed with sand, tape, mastic or wooden planks.
It is
a good practice - though one not always followed - to moisten
the surface of the concrete with an atomising spray of water
immediately prior to placing of the sheeting on the concrete. |
 |
 Mechanical barriers should be
placed over concrete as soon as the surface is
set. |
Water addition curing
Theoretically, flooding, ponding or mist spraying are better than
the retention methods mentioned above. But they are not always
practical because of job conditions.
On roads, pavements or floors, the method of flooding or ponding
is simple. A small dam of earth or other water retaining material is
placed around the perimeter of the surface and the enclosed area is
kept flooded with water.
Continuous spraying with water, while somewhat easier to control
than ponding, is subject to such difficulties as nozzle clogging and
loss of water pressure. In the spraying method the water is forced
through horizontal pipes to various locations and out through
nozzles which disperse it over the concrete surface.
Fogging is essentially the same, but the
nozzles deliver a finer, mist like spray.
Both methods
are affected by changes in wind velocity, which can
considerably reduce their effectiveness.
Care should be
exercised to prevent large temperature differentials between
the concrete mass and curing environment so as to avoid
potential cracking due to temperature gradients within the
concrete. This is generally known as thermal shock cracking. |
 |
 Flooding with water is
effective but can be impractical on some
sites |
Absorptive covers
An absorptive medium such as sand, hessian or canvas will hold
water on the concrete surface while curing progresses.
Any such medium must be kept damp constantly
during the curing period, for if drying is permitted, the
cover itself will absorb moisture from the concrete. Alternate
drying out and wetting of the cover may cause
cracking.
The use of sawdust as a cover is not
advisable, for it has on occasion retarded the hardening of
the concrete through the action of sugar in the sap still
present in the sawdust. |
 |
 Water can be retained longer by
using an absorptive cover. |
Structural concrete
The curing of structural concrete does not present as many
problems as may be experienced in curing thick floor slabs or
pavements, because the exposed surfaces are usually smaller.
Many concrete structures receive no curing other than that
effected by leaving forms in place for several days. The insulating
value of formwork is self-evident, but as a curing medium formwork
is effective only for the first day or so. As drying proceeds, water
vapour can escape along the gaps between the forms and concrete, as
well as through gaps between boards.
If formwork is to have a complete curing function it must be kept
wet continuously.
Exposed surfaces of the structure should be covered with
tarpaulins, plastic sheeting or waterproof paper, and kept wet.
When a concrete structure is built without protection of any
kind, the concrete being allowed to harden while exposed by turns of
sunlight, evening temperatures, wind and rain, inferior strength and
durability of concrete frequently results.
Reasons for Curing
To sum up the advantages of careful control of moisture and
temperature in curing:
- The strength of concrete increases with age if curing
conditions are favourable. Compressive strength of properly cured
concrete is 80 to 100 per cent greater than the strength of
concrete which has not been cured at all.
- Properly cured concrete surfaces wear well.
- Drying, shrinkage, cracking is reduced.
- Greater watertightness of constructions is assured.
Points to keep in mind when curing:
- Start curing operations as soon as possible after concrete has
been placed.
- For proper curing concrete needs moisture.
- Continuity in curing is a must; alterations of wetting and
drying promote the development of cracking.
- If during curing the concrete is allowed to dry out - as may
happen in hot weather - the chemical stops right at the point
where the concrete loses its moisture.
- The ideal curing temperature is 23°C.
- Cure concrete for at least 7 days.
The vicious cycle in inadequate curing must be obvious. If enough
water evaporates from the concrete before it has attained its
maximum strength, there will not be sufficient water remaining in
the concrete to fully hydrate the cement and so achieve that maximum
strength.
|
| |
| »Top |
|
The Effect of Excess Water in Concrete
Nothing is easier than adding excess mixing water to premixed
concrete at building sites. And nothing is more likely to reduce the
strength of the concrete, or make repairs to a concrete construction
necessary, or more likely to damage a contractor's reputation for
efficiency and reliability.
Concrete supplied by Ahlcon RMC is carefully proportioned and mixed to
produce strength according to specifications. Less than half the
water it contains is needed for the hydration of cement. The rest of
the water is there to make transporting and workability easier (by
providing lubrication between sand/aggregate particles) and to
ensure that there will be sufficient inherent water for the curing
process.
The plant supplying the mix will adjust the water content
fractionally to meet summer or winter conditions of transporting and
placing.
"Wetness" of concrete as measured by the slump test is directly
related to its compressive strength - the 28 day compressive
strength of concrete is reduced by about 1.5 MPa for each additional
20mm of slump produced by adding water.
To put this another way, each additional 10 litres of water per
cubic metre will reduce the strength of concrete by about 2.5
MPa.
Unless extreme conditions make it necessary, site supervisors
should not permit water to be added to premixed concrete without
their approval.
The ever present site problem is that all members placing teams
quickly learn about the labour saving effect that "a little" added
water has on workability of concrete.
The site supervisor can't tie knots in the hose(s) needed for
cleaning equipment so 'a little' water may be added to concrete
during a pour.
With this unofficial system operating it doesn't take long to add
100 litres of water to a truck load say (5m3) of mixed concrete. The
effects will be (a) an average increase of about 80mm of slump over
the slump specified, (b) an average reduction in compressive
strength of about 5 MPa and (c) uneven strength throughout the
concrete mass comprising a number of truck loads with varying
slumps.
The only answer is to make at least one responsible member of
each placing team fully aware of the harm excess water can
cause.
Perhaps the most dangerous of all practices is the use of extra
water to help concrete "flow" along elevated forms to lower points.
In this case, if shores/toms are removed after a normal curing
period, severe structural cracking and/or collapse are more than
possibilities.
Effects of too much mixing water
Whilst adding water will in some cases facilitate easier placing,
the disadvantages of this include the following:-
- Lower compressive strengths
- Segregation of the concrete mix under certain conditions
resulting in variable quality throughout the concrete mass.
- Cracking - with too much water, there will be lower tensile
strength, and a tendency towards high shrinkage and subsequent
cracking.
- Dusting and scaling - Bleeding of excess water brings too many
fines to the surface of floors
- Sand streaks. Excess water bleeding up the sides of forms
washes out cement paste and leaves an unsightly streaked surface.
- Contamination. Too much water in concrete placed on grades
causes contamination from the subgrade with the concrete leading
to an array of quality problems
- Permeability. Voids left as excess water evaporates invite
water to seep through walls and floors
- Dead losses - costly repairs, or in extreme cases, demolition
and re-building at contractor's expense.

Approximate compressive strengths for given water-cementitious
ratios are shown below. Cementitious binder needs less than half its
own weight of water to turn concrete into durable construction
material.
The 'wetter' this cementitious paste is, the weaker it is. The
chart below shows how strength decreases as water content of a mix
increases.
Four ways to minimise temptation to add excess
water
Be ready to accept premixed concrete as it
arrives. Prolonged mixing in the truck agitator makes concrete
stiffer, and harder to work.

Where high slump concrete or
special placement conditions exist consult Ahlcon RMC Technical
staff for advice about mix designs.
|
 |

All concrete requires proper
compaction using correct equipment and techniques.

Make sure that enough men are
available on site to transport , place, compact and finish
fresh concrete. |
| |
| »Top |
| |
Step-by-Step Guide to Laying Concrete
|
1. Lay out the project |
 |
|
Using stakes, twine, a tape measure and a level, stake out
the boundaries. Be sure to consider such factors as drainage,
nearness to tree roots and sufficient space for forms. Now you
are ready to remove the topsoil and level out the area, taking
dirt from the high places to fill the low spots. Remove enough
soil from around the edges to permit room for slab
forms. |
 |
 |
 |
|
2. Build strong forms |
 |
 |
Path or patio forms are usually made with planks set on the
edge and braced with heavy stakes on the outside, at 300mm
intervals. Spreaders may be staked in to be removed after the
concrete is placed. Reusable forms should be precoated with
oil or varnish. Take care not to use coatings which might
stain the concrete. For good drainage, pitch the surface 10mm
per metre in the desired direction. The sub-grade and the
forms should be thoroughly soaked the night before the pour
and dampened again before the truck arrives. |
 |
|
3. Make way for the truck |
 |
|
A 5 m3 concrete truck is 2.4 m wide, 3.3 m high and loaded
weighs about 20 tonnes. The truck is approximately 8m long
with a turning circle of 11m. Before directing a truck onto
your property make sure that it will not pass over any dry
wells or other hidden weak spots. Protect your lawn or
driveway by laying down planks for the truck to pass over. If
the truck is to be driven between the forms over the
sub-grade, use of planking will help to avoid deep ruts. If
you are building a driveway, make sure the forms are wide
enough for the truck to drive between them. This will greatly
expedite placing and save you the trouble of transporting the
concrete in a wheelbarrow. |
 |
 |
 |
|
4. Have some help available |
 |
 |
You will save time and money if you
are ready for the truck when it arrives. This means having all
preliminary work done and sufficient tools and help on hand to
handle the concrete. Among the tools you will need are several
shovels, one or two rakes, a 100mm x 50mm timber for
screeding, wood floats, steel trowels and a grooving tool. You
will need help shovelling the concrete into place as it comes
down the chute from the truck. One or two able-bodied friends
will make good assistants and help you reduce truck waiting
time charges. |
 |
|
5. Placing the concrete |
 |
| Trucks cannot always get close enough to place
the material where you want it. A deep tray contractor's
wheelbarrow with rubber tyres can be hired for this purpose.
Be sure to use planks to roll the wheelbarrow over to avoid
jarring the contents and to make your job of pushing it
easier. Compact the concrete thoroughly with shovels. Avoid
segregation and contamination with the subgrade material.
Loads should be placed so that they overlap or flow into each
other when tipped. Remember, concrete is heavy. Do not risk
hurting yourself by attempting to move more than you can
comfortably wheel in the barrow. |
 |
|
6. Screeding |
 |
| When the concrete is placed you are ready to screed it.
This is done by running a 100mm x 50mm timber section across
the surface in a sawing fashion, preferably with one man at
each end of the board. A third person could work ahead of the
board filling low spots and removing the concrete which
collects as the screed board moves forward. A deeper section
of timber (150mm) may be required when screeding wide
sections. |
 |
 |
 |
|
7. Floating |
 |
 |
The next step in the placing
operation is floating. The purpose of floating is to agitate
the surface, to compact the material and bring enough mortar
to the surface to fill the voids. A float can be home-made (a
piece of hardwood 300mm x 100mm with a wooden handle) or
purchased from a supplier. Use it with some light pressure and
tilted slightly upward. Floating provides a non-skid
surface. |
 |
|
8. Surface finishing |
 |
| Do not attempt surface finishing until the sheen has left
the concrete and it has hardened enough to permit a steel
finishing trowel to pass over it without digging in or causing
water and cement to be brought to the surface. Kneel on a
board to reduce pressure on the wet concrete surface. When the
job is done, thoroughly rinse your tools so they'll be usable
for other projects. If there is a risk of rain or of damage
from cold weather, cover the concrete with hessian or plastic
sheets, as soon as it can be done without damaging the
surface. |
 |
 |
 |
|
9. Contraction Joints |
 |
 |
The purpose of contraction (and
expansion) joints is to provide a plane of weakness so that
cracks which appear in concrete due to shrinkage tend to
follow these planes and be hidden. To ensure that this occurs
it is essential that grooves be no more than 2m apart and that
they be cut deeply. (normally 1/4 - 1/3 slab depth). Grooving
tools are cheap and ensure that your finished job has a
professional look. |
 |
|
10. Curing the concrete |
 |
| If concrete dries out too quickly it will crack
and lose strength. It is necessary to extend the drying out
time by keeping the concrete moist for at least seven days.
This can be done using a variety of techniques, advice on
which can be obtained from your local Ahlcon RMC office. Curing
must be started immediately after the 'set' has taken place,
say four to six hours, depending on climatic conditions. |
 |
 |
 |
|
11. Removing formwork |
 |
 |
When the concrete has enough strength
to support the weight it must bear (seven days) strip the
forms away. Do not use a metal tool against the surface to pry
off forms because you may cause damage. |
 |
|
How to measure your quantities |
 |
| The calculator below shows the approximate
amount of concrete you will need for your job. To use, measure
the length and width of the area to be laid in metres; find
the average depth to be filled and read off the calculator to
find the volume of concrete in cubic metres that you will
need. |
 |
As concrete is sold in units of 0.2m² the quantities have
been adjusted accordingly.
The tools you
need
Most of the equipment you need for laying
concrete can be hired.
- Deep barrows with rubber tyres
- Planks to wheel the barrows on
- A screed board
- Shovels
- A wooden float
- A mallet
- A steel trowel
- Grooving tool
- Spirit level
- A tamping tool
- Timber for formwork
- A rake
|
 |
 |
 |
|
Technical Advice |
 |
By following the procedures in this publication
and exercising proper care you will obtain the best
performance from your Ahlcon RMC concrete. Ahlcon RMC Technical
Bulletins and advice are readily available from your nearest
Ahlcon RMC Group office to assist in achieving the best possible
results.
Note: If reinforcement, membranes, insect
treatment sprays, or any special techniques are to be used,
seek specialist advice from experts in those fields as this
brochure is only a basic guide to laying concrete.
WARNING: Concrete is a highly alkaline
substance. Prolonged skin contact can cause severe irritation.
The use of gloves and gumboots is strongly recommended.
|
| |
| »Top |
|
|
General Purpose Blended Cement (Type GB)
A type of cement produced by combining Portland Cement with
supplementary cementitious materials such as fly ash, ground slag
and/or silica fume in varying proportions (typically ranging between 5%
and 60%) to produce a blended cement. Described in Ahlconn Standard
AS3972. The three most common supplementary cementitious materials used
are:
- Ground Granulated Iron Blast Furnace Slag (Slag): see Ground Slag
A by-product of the steel industry.
- Fly Ash
A by-product of coal-fired power stations producing electricity.
- Silica Fume
A fine powder collected from the process of silicon metal manufacturing.
General Purpose Portland Cement (Type GP)
A general purpose cement which is described in Ahlconn Standard
AS3972. Produced from grinding cement clinker (silica, alumina and iron
based components fused at high temperatures around 1500 degrees celcius
that produces a rock type material called clinker).
Granolithic Topping (Grano)
Normal concrete with 7 mm maximum size aggregate. Used mainly for
surfacing floors, concrete repairs, infills and cavity walls. |
High Early Strength Cement (Type HE)
High Early Strength Cement as defined under AS3972. A cement that
develops strength more rapidly (not to be confused with setting time)
than General Purpose Cements. Cement compressive strengths are
determined by casting cubes of mortar (cement mixed with water and a
specified sand).
Hot Water
Performs similar function to N.C.A (Non-chloride Accelerator). Can be used in lieu of, or in addition to, as a setting aid.
Hydration
The chemical reaction which takes place as a result of combining cement
and water. Maximum hydration equals maximum potential strength of
concrete. |
In Situ Concrete
Is concrete when placed in its final position.
Indirect Tensile
A strength test that measures a concretes resistance to being pulled
apart (called an indirect tensile test and described in AS1012). Tested
by applying a compressive force to a concrete cylinder specimen placed
on its side. |
Kerb and Channel (K&C)
Mix with a high sand content with a very low slump (0-30mm) which is
placed by a machine. Normally forms the edge of a pavement to direct
drainage. Normally maximum size aggregate is 14mm.
Kibble
A bucket for holding and transferring concrete from the agitator truck
discharge point to placement point. Commonly lifted by a crane (crane
& kibble). |
Lean Concrete
Low strength concrete (low cement content) used for non-structural
applications such as fill, or as a sub base for concrete pavements.
Also called lean mix concrete.
Lightweight
Low density concrete using light weight aggregate (scoria) or BST
(Polystyrene Beads). Density is usually less than 2100 kg/m3.
Low Heat Cement (Type LH)
As its name implies, generates less heat during hydration or hardening.
Used mainly in mass concrete pours such as raft slabs and dams to
prevent thermal cracking. Can also be used in high strength concrete
where early strength gain is not important. Often has supplementary
cementitious materials included in the blend. |
Mass Concrete
Refers to a concrete element that has a substantial cross section
(typically greater than 600mm thick). The greater the thickness of the
element, the greater the rise in temperature of the concrete after
placement (concrete gets hot as the cement and binder materials hydrate
and gain strength). Usually, special design and construction methods
are needed and this often results in the development of special mix
designs.
Megapascals (MPa)
Metric unit of measuring compressive strength of concrete. Described in
Ahlconn Standards AS3600 and AS1012 (example 20 MPa or 32 MPa).
Membrane
See Polythene
Mesh
Reinforcement which consists of bars (technically referred to as wires)
of steel spot welded together to form a mesh. The sizes given to the
mesh refer to the wire diameter and wire spacing e.g. F62 is a wire
diameter of 6 mm spaced at 200 mm centres. Microstrain
A length change measurement usually of drying shrinkage of concrete
using a specified concrete prism size described in AS1012. Concrete may
have a specified maximum drying shrinkage criteria described as a unit
of microstrain. Basically calculated by measuring a final specimen
length referenced to an original specimen length.
Mix Design
The process of combining materials in to specified proportions used in
producing concrete. Considerations include specified properties such as
strength, plastic properties such as bleeding, setting times, customer
satisfaction and materials available and costs.
Mixing Time
The time taken to satisfactorily mix a load as per agitator manufacturer's specifications.
Mixing Water
Water added to concrete at time of batching to enable hydration of cement and provide a workable mix. |
NCA (Non Chloride Accelerator)
A chloride free aid to accelerate setting time of concrete. Dosage
rates can vary from 0.5 litres to 6.0 litres per metre depending on
circumstances and specifications.
No Fines Concrete
Concrete made with coarse aggregate and cement (up to 10%).
Normal Class (N) Concrete
Concrete described in AS1379 specified by standard strength, standard
slump and standard maximum size aggregate. Standard strength
grades are N20, N25, N32, N40, N50 and standard slumps are between 40
mm and 120 mm. |
Pattern Paving
Mix with high sand content normally 10mm aggregate. Concrete mix
enables patterns of various designs to be created on the concrete
surface. Colour usually added.
Plastic Concrete
Concrete that is still capable of being worked and has not reached initial set (see set time).
Polythene
Thin plastic sheet placed on ground below a slab prior to placement of
concrete to prevent seepage of ground water up through the concrete and
to prevent moisture loss from the concrete being absorbed by the
sub-base (selected fill material placed immediately below a concrete
slab). High moisture loss can cause cracking and reduction of strength
of concrete.
Pozzolanic Material
A material like fly ash or silica fume that reacts chemically with lime
produced from cement hydration resulting in concrete strength gain.
These materials are used to supplement cement and are termed
supplementary cementitious materials. When combined with Type GP cement
they form Type GB cement (blended cement). Materials described in
AS3582.
Precast Concrete
Concrete that is cast and cured in moulds and shifted into the final
position. Generally enables better quality control and surface finish.
Prestressed Concrete
Specially designed concrete elements like slabs and beams that have
compressive forces applied by the tensioning of prestressing cables
(strands – used as part of the reinforcement). The strands may be
pre-tensioned (tension before casting) or post-tensioned (after
casting). Prestressed concrete enables larger spans between columns,
greater loads, minimal cracking and fast construction cycles. It can be
a more economical construction solution on a project depending on the
application. |
Reinforced Concrete
Concrete is strong in compression but weak in tension. Therefore most
concrete is reinforced with steel to improve the tensile strength of
the finished concrete element. Reinforcement in concrete is also used
to limit cracking by other forces such as shrinkage effects.
Reinforcement (Reo)
Welded wire steel fabric or steel bars used in concrete to control cracking and to meet structural loading requirements. |
S.S.D. (Saturated Surface Dry)
Refers to the condition of aggregates (coarse and fine) that have been
soaked in water and the excess water (surface water) removed. SSD
figures are used in designing mixes. It is the state of the aggregate
where maximum absorption of water has occurred and there is no free
water present. SSD density is higher than the density of the aggregate.
Sand Moisture Test
Test performed by completely drying out a small sample of sand to
ascertain the percentage of water it contains. Mixes can then be
adjusted accordingly for water content (see water:cement ratio).
Screeding
Process of levelling freshly placed concrete ready for surface
finishing (the process for establishing the final surface of a concrete
element).
Segregation
The separation of fine and course aggregates and other finer fractions
in a concrete mix. This is not desirable in supply of concrete. It can
typically result from poor mix designs, aggregate shape, excessive
slump, over-vibration, poor compaction and/or placement methods.
Self Compacting Concrete (SCC)
Concrete that specifically designed and is modified with specialty
admixtures to provide a free flowing concrete that requires little or
no compaction. Is normally specified where the use of vibrators is
difficult due to congestion of steel reinforcement or where restricted
by formwork.
Set Time (Setting Time)
Time taken for concrete to lose its plasticity and workability and
stiffening (initial set). Defined in AS1012 (Methods of Testing
Concrete). Setting times can be increased (by retardation) or reduced
(by acceleration) in various ways, e.g., by use of chemical admixtures,
hot water, using different types of cements and other binders and
increasing cement content.
Shotcrete
A concrete product designed to be pumped and sprayed using compressed
air through a nozzle. Normally has a slump of 60mm and is used for the
construction of concrete swimming pools, walls, bank stabilisation etc.
Sometimes referred to as Gunite which was an old outdated reference to
manufacture and supply of this material at a construction site.
Shrinkage
A very misunderstood term in our industry. Occurs in all concrete
whilst fresh (plastic shrinkage) and in its hardened state (drying
shrinkage). It relates to concrete volume change resulting from water
loss whilst the concrete is fresh and to concrete volume change
resulting from the hydration process and from drying of concrete once
the concrete is hard (in its hardened state). Shrinkage can be
marginally reduced by using the maximum amount of course aggregate
permitted in a mix and keeping the concrete moist (curing) as long as
possible during setting. Construction site practices have a major
influence on shrinkage.
Slag (Ground)
A product produced simultaneously with iron in a blast furnace that is
quenched (cooled rapidly with water) and ground to produce a
supplementary cementitious material that is used in concrete. Termed
ground granulated iron blast furnace slag and described in AS3582, it
can be incorporated into concrete directly or as a blended cement. It
can provide concrete with many beneficial properties.
Slag Aggregate
A product produced simultaneously with iron in a blast furnace that is
cooled naturally (not quenched). The material forms a rock like
structure that is crushed to result in an aggregate material that can
be incorporated into a concrete mix. Slag aggregates can impart
beneficial properties to concrete.
Slump
A measure of the consistency of workability of concrete and is a simple
means of ensuring uniformity (of a given mix) of concrete on site. The
test procedure is described in AS1012 (Methods of Testing Concrete).
Slump Test
Slump Cone
A test where a standard size steel slump cone is filled with plastic
concrete, procedures for which are described in AS1012. The cone is
them removed from the concrete to allow it to "SLUMP". The difference
between the height of the cone and the collapsed concrete is measured
in millimetres and is termed as the concrete slump. A typical concrete
slump is 80 mm. Normal Class concretes have slumps in the range between
40 mm and 120 mm.
Slurry Mix
Mix of sand and cement at varying ratios 1:2 -> 1:10. Slump depends
on application. Used for trench fill or block core fill.
Special Class (S)
Concrete which is specified to have certain properties or
characteristics different from or additional to those of Normal Class
concrete.
Standard Deviation
A statistical measurement which indicates the amount of variation.
Commonly used for 28 day concrete compressive strength result analysis.
A good result is a SD of less than 2 MPa.
Strength Grade
Is the numerical value of the characteristic strength of concrete
tested at 28 days. Designated by N20, N25, N30, N40 or N50 in the case
of Normal Class concretes. Refer characteristic strength and normal
class concrete.
Sulphate Resistant Cement (Type SR)
Sulphate Resistant Cement which provides additional protection where
the concrete is subject to an aggressive environment rich in sulphate
(sulphate attack is a chemical attack detrimental to concrete).
Superplasticiser (SP)
An additive used in concrete to aid placement in difficult
applications, e.g., where structure has large quantity of
reinforcement, or where reinforcement is very close together or where
structure has narrow opening. Increases workability (slump) of concrete
without negatively affecting strengths. |
Target Strength
The average strength the concrete is designed to achieve. For Normal
Class concrete mixes, target strength is the characteristics strength
plus 1.65 times the standard deviation i.e., TS = f'c + 1.65 x SD.
Parameter used by concrete technical managers to manage concrete
quality in terms of strength performance.
Topping
Is the process of laying concrete over existing concrete. Toppings can
be bonded (to the surface) or non-bonded. Special construction
considerations are essential for all topping applications. |
Water: Cement Ratio
Water: Binder Ratio
The relationship (ratio) between the amount of water and cement in
concrete. Often also referred to as water:cementitious or water:binder
ratio as most concretes now contain some amount of supplementary
cementitious materials. The lower the water:binder ratio, the greater
the durability and higher the strength of the concrete.
Water Reducer (WR)
Chemical admixture which reduces the amount of water required to
achieve a nominated slump. As the ultimate strength of concrete depends
on the quantity of water in the mix (i.e., water:binder ratio). It is
possible to achieve target strengths using less cement. Also enables
control of setting times to what is desired for construction.
Waterproof Concrete Additive (Waterproof Additive)
These are chemical additives that are added to concrete to impart
properties to limit water ingress, many of which are unsubstantiated.
The terms "waterproof" and "impervious" cannot be applied to a material
like concrete. A more correct term for this application is
"watertight". In saying that, there is still a lot of confusion as to
what "watertight" actually means. Usually, an engineer, contractor and
concrete supplier are needed to produce effective solutions on projects
even where speciality "watertight" concrete admixtures are used. |
Yield
The determination of the actual volume of concrete used versus the
theoretically determined volume to confirm or establish theoretical mix
design volumes. |
|